Shipping and freight forwarding · Practical guidance for overseas businesses and law firms · Prepared 23 November 2026
A logistics provider can arrange a shipment, issue a transport document, engage another agent and collect freight. Which of those acts it performs matters when a dispute arises. The company’s description as a “freight forwarder” does not resolve whether it owes agency duties, carrier obligations or both in a particular transaction.
Map the undertaking shipment by shipment
Start with the quotation, booking instruction and acceptance. Identify what was promised: arranging space, carrying cargo, customs handling, storage, documentary work or delivery by a particular date. Establish the principal, any disclosed carrier and the extent of the forwarder’s discretion.
Use a simple evidence table: obligation, person giving the instruction, accepting company, performance record, alleged failure and resulting loss. This separates a disputed instruction from a failure in performing an accepted instruction. It also reveals where the claimant has documents only from a downstream agent.
Examine the transport document and signing capacity
Obtain the complete house and master documents, including reverse terms, electronic versions and the issuer’s signature block. Establish whose name appears as carrier and whether a signature was made as an authorised agent. Preserve the document as issued, rather than a later summary prepared for accounts.
The SPC maritime forwarding provisions distinguish agency arrangements from circumstances involving carrier liability, including the capacity in which transport documents are issued. Read the provisions with the 2020 amendments. A company’s role must be supported by the actual agreement and conduct, rather than assumed from its licence or website.
Reconstruct authority and delegation
Identify who was authorised to book, amend the destination, release documents or request a telex release. Keep the original emails, attachments and relevant messages. Where instructions came through an overseas agent, identify whether that agent acted for itself or for a disclosed customer.
Subcontracting adds a separate question: was it permitted, what was delegated and what obligations remained with the original provider? Supply the relevant consent and terms. The presence of another agent in the chain does not automatically release the first provider or make every participant responsible for the same loss.
Connect the breach to the loss
For a missed vessel, establish the booking cutoff, agreed information or document deadlines, the time the necessary material was supplied and the reason the cargo was not loaded. For a release error, reconstruct control of the relevant documents and the instruction actually received.
In a hypothetical claim, a customer alleges that a forwarder caused ten days’ delay. If the booking was confirmed only after the cutoff and customs documents were incomplete, the entire storage bill cannot simply be attributed to one late email. A dated chronology allows the parties to assess causation and any contribution to the loss.
Support the amount and identify possible limits
Distinguish prepaid freight, agency fees, reimbursable advances and damages. Match additional charges to tariffs, invoices and proof of the obligation or payment. Record insurance recoveries and any recovery from another participant. Avoid double counting the same cargo value across several claims.
Contractual exclusions, limits and notice requirements need review for incorporation, scope and enforceability. Where carrier liability or another maritime regime is engaged, special rules may matter. The revised Maritime Law took effect on 1 May 2026; earlier and continuing facts require the temporal analysis described in the SPC interpretation.
Decide the procedural route before negotiating a release
Maritime forwarding disputes may belong in a maritime court, subject to the applicable dispute clause and jurisdiction rules. A separate non-maritime service may require a different analysis. Check limitation early, rather than importing an ordinary invoice deadline into a cargo-related dispute.
If goods or documents are being withheld, assess release and retention rights separately from damages. A settlement should specify the cargo or document to be released, the charges paid under reservation, the remaining dispute and how performance will be verified. The objective is a supported allocation of responsibility that also prevents an unresolved fee dispute from generating avoidable additional losses.
Legal sources and scope
This article concerns mainland China and provides general information. Practical recommendations should be assessed against the facts of each matter. All hypothetical examples are illustrative and do not describe client cases. Legal sources were checked on 23 November 2026; the relevant dates, current rules and applicable treaty relationships require case-specific review. Linked Chinese legal texts control where applicable.
- SPC provisions on maritime freight forwarding disputes (read with the 2020 amendments)
- SPC 2020 amendments to commercial judicial interpretations, item 29
- PRC Maritime Law (2025 revision; effective 1 May 2026)
- SPC rules on the temporal application of the revised Maritime Law
Related practical guides
- Shipping Disputes Involving China: Which Court Has Jurisdiction?
- Unpaid Freight Charges in China: Who Is Liable and How Can They Be Recovered?
- Cargo Detained or Not Released in China: Legal Options for Overseas Businesses
- Cross-Border Evidence in Chinese Courts: Documents, Electronic Records and Authentication
Browse all cross-border dispute guides by topic
Discuss your matter
For an initial enquiry, provide the parties’ legal names, a short chronology, the amount involved, the dispute resolution clause and any approaching deadline. Please obtain conflict clearance before sending a full confidential case file.
Contact Sun Wansong · Commercial debt recovery services · More practical guides